On Thu, 2014-07-17 at 14:51 +0800, Daniel Veillard wrote:
Plan is to get the new release on Friday Aug 1st, so
I think this mean entering freeze at some point on the
preceeding week-end, I will be travelling then, but I
should be able to do that at some point saturday 26.
We already have 180 commits in since 1.2.6 so deinitely
makes sense to push this month too,
It would be good if someone could push my 3 patches around LXC keep/drop
capabilities before 1.2.7 freeze. Those were ACKed by Daniel during
1.2.6 freeze.
--